BAPTIST CHURCH

Baptist church roof replacement- Project of the Year Winner 2021
Church with new roof after severe hail damage

PROJECT OVERVIEW

A spring hailstorm in the Waco area affected many downtown roofing systems. After discovering damage on several adjacent buildings, Target notified the administrative staff. Upon inspection, it was discovered that a baptist church suffered a loss constituting the replacement of the entire roof assembly at the church and neighboring daycare facility. 

Many of the church roofs were multiple-layered overlays, the result of decades of deferred maintenance and neglect. Target successfully interfaced with the insurer to achieve an appropriate valuation to the roof system and began work.

After removing the old assemblies, Target installed new code-compliant insulation, recovery board, and a 60mil Sika/Sarnafil PVC membrane roof system. Target also replaced the shingle roofs and oversaw the removal and upgrade of outdated HVAC systems and electrical components. The project was projected to take over 4 months, but Target completed the entire scope of work ahead of schedule. This project was awarded 2021 Sika Sarnafil Project of the Year.

TURNKEY SERVICES

  • Mitigation
  • Removal and replacement of all shingled roofs
  • Removal, code upgrade & replacement of all single-ply roofs
  • Detachment and reset of high-efficiency VRF HVAC system
  • HVAC upgrades
  • Electrical upgrades
  • Interior and exterior repairs addressing wind damage

PROJECT HIGHLIGHTS

  • This project won Sika Sarnfil's 2021 Project of the Year
  • No safety incidents reported
  • Our team worked closely with the insurance adjuster, building consultants, engineers, HVAC experts and electricians
  • Project was finished 30 days ahead of schedule